Navy Contract LawBureau of Naval Personnel, 1949 - 301 páginas |
Dentro del libro
Resultados 1-5 de 100
Página
... prior to the execution of any negotiated contract the Secretary of the Navy shall find and determine that the price or prices included therein are fair and rea- sonable . ment . By Navy directive dated July 5 , 1940 , * provision was ...
... prior to the execution of any negotiated contract the Secretary of the Navy shall find and determine that the price or prices included therein are fair and rea- sonable . ment . By Navy directive dated July 5 , 1940 , * provision was ...
Página 2
... Prior to World War II , Navy procurement was governed by an astonishing mass of undi- gested and uncoordinated legislation - statutes that had accumulated on the books over a pe- riod of more than one hundred years . Many were ...
... Prior to World War II , Navy procurement was governed by an astonishing mass of undi- gested and uncoordinated legislation - statutes that had accumulated on the books over a pe- riod of more than one hundred years . Many were ...
Página 5
... prior to the execution of any negotiated contract the Secretary of the Navy shall find and determine that the price or prices included therein are fair and rea- sonable . The effect of this personal and non - delegable grant of ...
... prior to the execution of any negotiated contract the Secretary of the Navy shall find and determine that the price or prices included therein are fair and rea- sonable . The effect of this personal and non - delegable grant of ...
Página 8
... prior conceptions , during the course of per- formance of work paid for by the Government . The problem became particularly acute as greater intensification of effort and emphasis was placed upon Government - sponsored re- search and ...
... prior conceptions , during the course of per- formance of work paid for by the Government . The problem became particularly acute as greater intensification of effort and emphasis was placed upon Government - sponsored re- search and ...
Página 9
... prior experi- mentation and development in the field for I which the Government did not pay . Further- more , a patented invention in the abstract is of little real value ; it is the constant develop- ment and reduction to practice ...
... prior experi- mentation and development in the field for I which the Government did not pay . Further- more , a patented invention in the abstract is of little real value ; it is the constant develop- ment and reduction to practice ...
Otras ediciones - Ver todas
Términos y frases comunes
80th Congress advance payments agency agree agreement aircraft amendment amount applicable appropriation approved Armed Services Procurement award basis bidder Board Bureau Bureau of Aeronautics chapter claims clause Comp Comptroller construction contract price contracting officer contractor cost-plus-fixed-fee Court curement defense delivery determination disposal equipment eral ernment excessive profits Executive Order exemption expressly facilities Federal fiscal fixed-price formal advertising funds furnished Government industrial June 25 labor limited manufacture material ment Navy Department Navy procurement Navy's obligation Office of Naval patent performance permit Powers Act prior problem procedures production project order Public Law redetermination reimbursement research and development respect Secretary Section 2(c Services Procurement Act specific Stat statute statutory subcontracts Surplus Property Act termination thereof tion tract tractor type of contract U. S. Code United V-J Day vessel Vinson-Trammell Act War Powers Act World War II
Pasajes populares
Página 243 - No Executive Department or other Government establishment of the United States shall expend, in any one fiscal year, any sum in excess of appropriations made by Congress for that fiscal year, or involve the Government in any contract or other obligation for the future payment of money in excess of such appropriations unless such contract or obligation is authorized by law.
Página 86 - ... the debts due to the United States shall be first satisfied, and the priority hereby established shall extend as well to cases in which a debtor, not having sufficient property to pay all his debts, makes a voluntary assignment thereof, or in which the estate and effects of an absconding, concealed, or absent debtor are attached by process of law, as to cases in which an act of bankruptcy is committed.
Página 36 - All purchases and contracts for supplies or services in any of the departments of the Government, except for personal services, shall be made by advertising a sufficient time previously for proposals respecting the same when the public exigencies do not require the immediate deliveiy of the articles or performance of the service.
Página 68 - No contract shall be entered into for the erection, repair, or furnishing of any public building, or for any public improvement which shall bind the Government to pay a larger sum of money than the amount in the Treasury appropriated for the specific purpose (ft.
Página 42 - ... (2) when the public exigencies require the immediate delivery of the articles or performance of the service, (3) when only one source of supply is available and the Government purchasing or contracting officer shall so certify, or (4) when the services are required to be performed by the contractor in person and are (A) of a technical and professional nature or (B) under Government supervision and paid for on a time basis.
Página 130 - It is not necessary that Congress supply administrative officials with a specific formula for their guidance in a field where flexibility and the adaptation of the congressional policy to infinitely variable conditions constitute the essence of the program. 'If Congress shall lay down by legislative act an intelligible principle . . . such legislative action is not a forbidden delegation of legislative power.
Página 67 - Treasury to continue to receive, examine, and consider the justice and validity of all claims under appropriations the balances of which have been exhausted or carried to the surplus fund under the provisions of said section that may be brought before them within a period of five years.
Página 196 - Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the city, town, village, or other civil subdivision of the State in which the work is to be performed...
Página 147 - If an offer for a unilateral contract is made, and part of the consideration requested in the offer is given or tendered by the offeree in response thereto, the offerer is bound by a contract, the duty of immediate performance of which is conditional on the full consideration being given or tendered within the time stated in the offer, or, if no time is stated therein, within a reasonable time.