Opinion of the Court.

shall be ready to commence work, said work to be paid for as

the same progresses.

"We also hereby apply for a separate and a further contract for so much of the grading, hauling, and filling as is not embraced in the contract for paving, and for setting the curbing on the streets, to be paved by us at board prices, subject to the conditions of the paving contract.'

"Is this day accepted.

"By order of the Board:

CHARLES S. JOHNSON,
"Ass't Secretary."

The petition then alleges that in pursuance of said contract, and in part execution and performance thereof, said board of public works designated nine different pieces of work to be done by the company; all of which was done by it, to an aggregate amount of about 35,000 square yards, and that said company was prepared and ready to do all the rest of the 75,000 square yards specified in said contract, but that said board of public works failed and refused to designate any more work to be done by the company, whereby said company was damaged in the sum of $100,000; that said contract of December 10, 1872, was in effect ratified and confirmed, and the right of action thereon recognized and approved, by virtue of several acts and resolutions of Congress, among which are the act of June 20, 1874, resolution of December 21, 1874, act of March 3, 1875, joint resolution of March 14, 1876, act of June 11, 1878, and the act of June 16, 1880; and that the claims herein made were never rejected by the board of audit. The petition then alleges that on the 20th day of June, 1874, said W. W. Ballard and E. L. Marsh, for a full and valuable consideration, sold and assigned in writing all and singular their respective rights, interests, and claims in and to the cause of action herein set forth, whereby the plaintiff, Talmadge E. Brown, became the sole owner of said claim and cause of action, and is now the owner thereof, and has made no assignment or transfer of the same or any part thereof to any one, but still owns and holds the whole thereof in his own right.

Opinion of the Court.

The matters set up in the second, third, and fourth counts of the petition (which are, as claimant states, "only different forms of statement for the same claim") have relation to the work done by the pavement company under the alleged contract of December 10, 1872, amounting in value to $129,569.85, for which they received certificates of the auditor of the board that they afterward sold in the market for about 50 cents on the dollar, realizing therefrom only $69,784.92. The second count relates to the work actually done, and avers that only one-half thereof has been paid for. The third count sets up the doing of the work, and the issuance of auditor's certificates therefor, under such circumstances as are claimed constituted the company an agent for the District to dispose of the certificates at their value, which was 50 cents on the dollar. And the fourth count sets up the doing of the work, the issuance and delivery to the pavement company of auditor's certificates, which are claimed to have been chattels, and a commodity only, and which were worth 50 per cent of their face value. It is to recover from the District of Columbia the other half of the value of these auditor's certificates that the claimant brings this action on these three counts.

To this petition the District of Columbia interposed a genзral denial, and also a special plea to the first count thereof, which set up a former adjudication of the matters involved in said first count in the Supreme Court of the District of Columbia. Replication was filed, issue was joined, and the case having been heard before the Court of Claims, that court, upon the evidence, found in favor of the District of Columbia and rendered judgment dismissing the claimant's petition. The separate findings of fact of the court below are seventeen in number, and are too lengthy to be incorporated in this opinion. The material facts will be referred to as we proceed.

The decision of the Court of Claims was based upon three grounds: (1) That the contract sued on was not a contract made with the board of public works of the District of Columbia, and was not one in writing as contemplated in § 37 of the act of February 21, 1871, 16 Stat. 419, 427; (2) that the claim set up in the first count of the petition was res adjudicata, it hav

Opinion of the Court.

ing been once adjudicated by the Supreme Court of the District of Columbia adversely to the Ballard Pavement Company, of which the plaintiff below is the successor; and (3) that, under the act of June 16, 1880, § 8, 21 Stat. 284, 286, the Court of Claims was prohibited from taking jurisdiction of the claim set up in said first count, because that claim had been once rejected by the board of audit of the District of Columbia.

The decision of the court was clearly right, and the principles on which the learned judge based his conclusion are clear and undeniable.

The appellant contends that the alleged contract sued upon meets the requirements of § 37 of the act of February 21, 1871, which provides that "all contracts made by the said board of public works shall be in writing, and shall be signed by the parties making the same, and a copy thereof shall be filed in the office of the secretary of the District;" and that the contract sued upon being a formal proposition in writing, and an acceptance thereof in writing signed by the secretary of the board, whose authority to sign the same is not denied, and whose genuine signature thereto is admitted, was a valid contract binding upon the parties.

Numerous authorities are cited to show that the written acceptance by one party of a written proposal made to him by another party creates a contract of the same force and effect, as if formal articles of agreement had been written out and signed by said parties. The legal principle asserted is sound, but the fallacy of the argument lies in the assumption that the proposition of the pavement company was in fact submitted to the board, and that the latter did in fact authorize the letter to be written by secretary Johnson accepting the said proposition. Are these assumptions borne out by the evidence adduced at the trial? Upon this point we quote from the 2d, 3d, 4th, 5th, and 6th findings of facts:

"In the early part of that month, (December, 1872,) the said William W. Ballard and the claimant were in the city of Washington, and they had verbal negotiations with Alexander R. Shepherd, then and afterwards a member and vice-president of the board of public works of the District of Columbia,

Opinion of the Court.

which negotiations led them to write and send to that board a paper, a copy of which is given in the letter signed 'Charles S. Johnson, Ass't Secretary.' [This letter is quoted in the early part of this decision.] The said Charles S. Johnson was a clerk in the employment of the board of public works and was styled 'assistant secretary.'

"The journal of said board does not show that said proposition was ever before the board, nor does any acceptance thereof by the board appear otherwise than by the statement of said letter; nor does it appear that said Johnson was authorized by said board to write said letter, unless it should be inferred from his being a clerk of the board and styled assistant secretary; nor does it appear that the board or any member of it, except Alexander R. Shepherd, either saw or knew of said letter before or on the said 10th of December, 1872; nor can the original proposition, as drawn up by the claimant and said Ballard, be anywhere found among the papers or files of the board or of the District of Columbia, though searched for there; nor can any copy of said Johnson's letter be found in the books or files of the board or of the said District, though searched for there, and though it was the practice of the board to keep press copies of the letters that went out of its office.

"In all the transactions hereinafter set forth, connected with the matter of paving streets by the said company, it does not appear that any member of the company was before the said board, at any meeting thereof, in relation to that work. Their intercourse in regard to it was almost wholly with said Alexander R. Shepherd. It took place sometimes at his store and sometimes at the office of the board. When it took place at his store it does not appear that any other member of the board was present; when it took place at the office of the board, if other members of the board were present, and any member of the company spoke to them about the matter of that work, they would refer him to said Shepherd. When the company desired work to be designated for them to do they called on said Shepherd, supposing that whenever he said anything about the work in the District he represented the board

Opinion of the Court.

of public works-was the mouthpiece of the board. The said company, after receiving said Johnson's letter, proceeded to make preparations for laying down wooden pavement on streets in the District of Columbia, and made a contract for three million feet of lumber, estimated by them to be sufficient to make 75,000 square yards of pavement. In the spring of the year 1873 the company notified the board, through said Shepherd, that they were ready to proceed with the work of paving streets, and requested that such work should be designated for them to do; but none was designated until the latter part of June or beginning of July, when some parts of streets were designated and the company entered on the work of paving them. After doing so, and before they were allowed to receive any certificates of measurement showing work to have been done, they were required to enter into a written contract embracing the work and to give bond for its performance. They at first declined to sign such a contract, claiming that the terms contained in it were different from those of their proposition of December 10, 1872; but they afterwards signed the following contracts."

The findings set out in full the contracts, and further show that the company entered into five of such contracts with the board of public works, the first bearing date July 5 and the last December 19, 1873; that all the work done by the company and every yard of pavement laid by it were done and laid under one of those several contracts; that every engineer's certificate of measurement gave on its face the number of one of those contracts as that under which the work named in the certificate had been done; that the company signed a receipt for every such certificate, and that upon those certificates the company received the auditor's certificates, which they voluntarily sold in the market for about fifty cents on the dollar.

In the face of these facts, found almost wholly from the evidence on the part of the claimant, we are of the opinion that we would not be justified in finding that the alleged contract of December 10, 1872- the one sued on here was such as the statute prescribes, or that it was a valid contract in any respect.