Cases Decided in the United States Court of Claims ... with Report of Decisions of the Supreme Court in Court of Claims Cases, Volumen125The Court, 1958 |
Dentro del libro
Resultados 1-5 de 23
Página xiii
... Panama Canal . ALABAMA FLAKE GRAPHITE COMPANY , GENERAL GRAPHITE COMPANY AND W. L. SHUMATE ( No. 48907 ) --- 635 Suit under Contract Settlement Act ; evidence fails to es- tablish liability of Government in erection of graphite plant ...
... Panama Canal . ALABAMA FLAKE GRAPHITE COMPANY , GENERAL GRAPHITE COMPANY AND W. L. SHUMATE ( No. 48907 ) --- 635 Suit under Contract Settlement Act ; evidence fails to es- tablish liability of Government in erection of graphite plant ...
Página 17
... Panama Canal Zone , the claim being based on changes in ocean freight rates during the period of performance ; it is held that plaintiffs are not entitled to recover . Recovery allowed the defendant on its counterclaim . United States ...
... Panama Canal Zone , the claim being based on changes in ocean freight rates during the period of performance ; it is held that plaintiffs are not entitled to recover . Recovery allowed the defendant on its counterclaim . United States ...
Página 18
... Panama Canal Zone . The contract price was $ 3,930,916 . The bid which was dated March 11 , 1940 , was opened March 12 , 1940 , and accepted on April 8 , 1940 , on which latter date a notice of award and a notice to proceed were issued ...
... Panama Canal Zone . The contract price was $ 3,930,916 . The bid which was dated March 11 , 1940 , was opened March 12 , 1940 , and accepted on April 8 , 1940 , on which latter date a notice of award and a notice to proceed were issued ...
Página 21
... of officers ' and noncommissioned officers ' quarters in the Panama Canal Zone at Fort Clayton and Albrook Field , for a consideration of $ 3,930,916 . Findings of Fact 125 C. Cls . 3. Plaintiffs ' TUCKER MCCLURE ET AL . 21.
... of officers ' and noncommissioned officers ' quarters in the Panama Canal Zone at Fort Clayton and Albrook Field , for a consideration of $ 3,930,916 . Findings of Fact 125 C. Cls . 3. Plaintiffs ' TUCKER MCCLURE ET AL . 21.
Página 22
... Panama Canal , will apply to the Contractor and his Sub - Contractors when the services and supplies are available , unless otherwise provided in these specifica- tions for particular services and supplies . Copies of the tariffs ...
... Panama Canal , will apply to the Contractor and his Sub - Contractors when the services and supplies are available , unless otherwise provided in these specifica- tions for particular services and supplies . Copies of the tariffs ...
Otras ediciones - Ver todas
Términos y frases comunes
Acme Acme's action agreement alleged allowed amended amount appeal application April Army August 14 Channel charter Civil Service Commissioner Company compensation contracting officer contractor Corporation cost Court of Claims damages December decision defendant defendant's motion determined dismissed employees entitled to recover equipment evidence excavation excess Executive Order February 21 filed Fill Area Findings of Fact follows Government contract grade graphite held HOLC income Indian Claims Commission Internal Revenue July July 13 June lease letter levee loan loss Lucas Act Malheur Reservation Maritime Commission ment November operation paid paragraph parties payment performance period pervious Philippines Piutes plaintiff prior railroad Reconstruction Finance Corporation request reservation resident engineer retirement salary Section September September 16 Shumate specifications Stat statute of limitations suit Swiss Federal Railways tiff tion treaty tribe United States 74 United States Court War Production Board Waxman wet material Wierum
Pasajes populares
Página 246 - In making the foregoing determinations the court shall review the whole record or such portions thereof as may be cited by any party, and due account shall be taken of the rule of prejudicial error.
Página 206 - ... (b) In the case of any such person who, in order to perform such training and service, has left or leaves a position, other than a temporary position, in the employ of any employer...
Página 145 - Candor and Fairness. The conduct of the lawyer before the Court and with other lawyers should be characterized by candor and fairness.
Página 327 - I will observe and obey the orders of the President of the United States and the orders of the officers appointed over me, according to the Rules and Articles of War.
Página 44 - In the case of the death of a taxpayer there shall be included in computing net income for the taxable period in which falls the date of his death, amounts accrued up to the date of his death if not otherwise properly includible in respect of such period or a prior period.
Página 249 - That the review by the court shall be limited to questions of law and that findings of fact by the commission, if supported by substantial evidence, shall be conclusive unless it shall clearly appear that the findings of the commission are arbitrary or capricious.
Página 50 - In the case of an individual, losses sustained during the taxable year and not compensated for by insurance or otherwise — (1) if incurred in trade or business; or (2) if incurred in any transaction entered into for profit, though not connected with the trade or business...
Página 859 - That hereafter the service of a cadet who may hereafter be appointed to the United States Military Academy, or to the Naval Academy, shall not be counted in computing for any purpose the length of service of any officer of the Army.
Página 322 - Abatement of tax for members of armed forces upon death In the case of any individual who dies on or after December 7, 1941, while in active service as a member of the military or naval forces of the United States or of any of the other United Nations...
Página 11 - Disputes. Except as otherwise specifically provided In this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.