" Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Página 502
1955
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen154

United States. Court of Claims, Audrey Bernhardt - 1968 - 922 páginas
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen141

United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 páginas
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be...
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen145

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 páginas
...plaintiff can escape the requirement that "Any claim by the contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...by the contractor of the notification of change," and the requirement that any disputes concerning a question of fact resulting from the change shall...
Vista completa - Acerca de este libro

The Code of Federal Regulations of the United States of America

1982 - 532 páginas
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as result of a change is included in the Contractor's...
Vista completa - Acerca de este libro

Code of Federal Regulations: Containing a Codification of Documents of ...

1982 - 690 páginas
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...
Vista completa - Acerca de este libro

The Code of Federal Regulations of the United States of America

1983 - 780 páginas
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...
Vista completa - Acerca de este libro

The Code of Federal Regulations of the United States of America

1967 - 686 páginas
...Any claim by the contractor for an adjustment under this clause must be asserted in writing within 30 days from the date of receipt by the contractor...any time prior to final payment under this contract. A failure to agree on an equitable adjustment under this clause shall be deemed to be a dispute within...
Vista completa - Acerca de este libro

Code of Federal Regulations: Containing a Codification of Documents of ...

1970 - 670 páginas
...shall be modified In writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...upon any such claim asserted at any time prior to «in«i payment tinder this contract. Where the cost of property made obsolete or excess as a result...
Vista completa - Acerca de este libro

The Code of Federal Regulations of the United States of America

1980 - 874 páginas
...shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt...receive and act upon any such claim asserted at any time pi.tr to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning...
Vista completa - Acerca de este libro

The Code of Federal Regulations of the United States of America

1972 - 220 páginas
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question...